Otley Storm Tank Clean

Gallows Hill | Leeds

5Tanks Cleaned
2Weeks Programme

Method of Works

VEGETATION CLEARANCE

Six years’ growth cleared from the site perimeter using specialist tracked machinery.

TANK DEWATERING

Standing water pumped down prior to sludge excavation.

SLUDGE EXCAVATION

25-tonne excavator mobilised to End B. Sludge pushed from End A toward End B using a Skid Steer.

SLUDGE STOCKPILE & LOAD OUT

Material stockpiled at End B and loaded into 20-tonne haulage lorries for disposal.

REPEAT FOR ALL 5 TANKS

Process repeated across each tank until all were cleaned to specification.

Project Summary

Delivered On Time. On Budget. To Specification

Foul water rising main successfully delivered, improving network performance and resilience with minimal surface disruption.

var(--variable-JCnovcc3T)
var(--variable-JCnovcc3T)
var(--variable-JCnovcc3T)

← All Case Studies

We have an experienced team with over 100 years’ combined experience in utility, civil engineering & construction sectors.

Copyright © 2026 MRMS. All Rights Reserved.

We have an experienced team with over 100 years’ combined experience in utility, civil engineering & construction sectors.

Copyright © 2026 MRMS. All Rights Reserved.

We have an experienced team with over 100 years’ combined experience in utility, civil engineering & construction sectors.

Copyright © 2026 MRMS.

All Rights Reserved.